Project No GTC/07/147/ED
Type EPIC
Title Engineering, Procurement, Installation and Commissioning of Desalinated Water Network Phase II at Ras Laffan.
Client Qatar Petroleum
Date of Completion 23/11/2009
Details This EPIC Contract construction of site survey, topographic survey, detailed design & engineering, procurement of materials such as MOV PCV, manual valves, electrical & instrumentation materials, civil works such as temporary facilities, leveling / grading, pipeline trench; construction of valve chamber, microtunneling , product corridor crossing, pipeline crossing, pipeline installation, instrumentation & control installation, testing of electrical & instrumentation / control systems, sterilization of pipeline, precommissioning and commissioning.
Project No GTC/07/146/ED
Type EPIC
Title Engineering, Procurement, Installation and Commissioning of Corrosion Inhibition Facilities at the Wellheads with Gaslift, Dukhan
Client Qatar Petroleum
Date of Completion 08/03/2010
Details EPIC for the Creation of Corrosion Inhibition Facilities at Wellheads with Gaslift - Dukhan.
The objective of the work is to provide corrosion inhibitor injection facilities for each individual Wellhead having Gas Lift facilities in order to protect essentially the Wellhead casing, tubing and flowlines from corrosion.
Project No GTC 06/133/ED
Type EPIC
Title Engineering, Procurement, Installation and Commissioning for the Replacement of Halon System at Dukhan and Mesaieed
Client Qatar Petroleum
Date of Completion 23/05/2009
Details This is a EPIC Project to replace the Halon System in various locations, replace existing Halon System in the turbine enclosure with Water Mist System, Installing HSSD Systems and integrate the new system with existing F & G ESD Systems and with DCS.
The project consists of site survey, design & engineering, procurement of materials, civil & structural works such as trenching of road crossing, etc.; Instrumentation works such as functional testing calibration, cabling, installation of instruments etc; Electrical works such as cable laying, install MCBs, DBs, etc.; Loss Prevention such as installation of HSSD panels, fire alarm system, etc.; DCS, ESD/F&G, HVAC, etc,; testing, pre-commissioning and commissioning.
Project No CT/RG27/L123/06
Type EPIC
Title Napthenic (Sulfidic) Caustic Injection Project
Client RASGAS
Date of Completion 15/04/2008
Details EPIC for the Sulfidic Caustic Injection Project at the Ras Laffan Site.
The project includes modifications and new works in various locations in and around the LNG Plant and include works on Trains - 1, 2, 3, 4, 5 and AKG-1.
Site survey, detailed design engineering, procurement of caustic filtration package, HCL acid dosing package, static inline mixer, pumps, tanks, pipes, valves, etc. Construction of RCC roundation, structural steel supports, excavation, pavement, asphalt road. Installation of caustic filtration unit, HCL acid dosing unit, static inline mixer, etc. including all the electrical and instrumentation work. Precommissioning and commissioning of all the equipment and instruments.
Project No GTC 07/178/ED
Type EPIC
Title Engineering, Procurement, Installation and Commissioning for Replacement of V-2003 and Installation of Air Coolers at NGL-2 Mesaieed
Client Qatar Petroleum
Date of Completion 31/05/2009
Details Design and detailed engineering, procurement of all materials including glycol separators V-2003 and iar coolers E-2410/S. The construction consists of earthworks, excavations, concrete foundations, structural steel, fabrication and erection of access road, transportation and erection of glycol separator and coolers, piping , cable laying, installation of control / ESD panels, calibration and installation of field instrument, installation of lighting and earthing system, installation of firewater monitors, F&G detectors, F&G panels, hydrotesting, pre-commissioning / commissioning, part shutdown, start-up and reliability test.
Project No QIGOO1.4 (GASAL)
Type EPIC
Title Works and Services Contract Mesaieed 1 - Nitrogen Pipeline
Client GASAL
Date of Completion 31/05/2009
Details The project consists of installation services for laying the 14” Nitrogen Gas Pipeline and its Control Stations.
The 14” Nitrogen Gas Pipeline is routed between Gasal Plant, located in QASCO premises, and consumers QATAFIN and Q-CHEM II, located in Mesaieed Industrial City. The pipeline is equipped with control stations at its export and receiving points with facility for Pressure Control and Metering.
Project No GTC 07/129/ED
Type EPIC
Title Engineering, Procurement, Installation and Commissioning of RAW NGL Facilities at Wellhead DK-568
Client Qatar Petroleum
Date of Completion 21/05/2008
Details The project consists of Engineering, Procurement, Installation of new piping and associated facilities to newly drilled injection well DK-568 and commissioning the same to fulfill the design capacity in a safe manner. The works include site survey, engineering, HAZOP, installation of concrete foundation, ESD valves, piping, instruments, cabling, fencing, paint, pre-commissioning and commissioning.
Project No MESAIEED I - ASU QIC1001.1
Type Construction
Title Construction and Commissioning of Nitrogen Plant
Client AIR LIQUIDE
Date of Completion 31/12/2007
Details The project is for the construction of a new air separation plant (nitrogen plant) at Mesaieed which consists of site preparation, procurement of materials, fabrication and erection of structural steel, installation of equipment shelters, installation of heavy equipment, fabrication and erection of piping systems, installation of instrumentation and electrical systems, painting, testing of all equipment and systems, pre-commissioning and commissioning.
Project No GTC/04/200/FSD
Type MANPOWER
Title Provision of Manpower for Dukhan Workshops on a Call-off Basis in the Dukhan Fields.
Client Qatar Petroleum
Date of Completion 15/12/2008
Details Provision for supply of Manpower for QP Workshops at Dukhan on a Call-off Basis.
Project No 3000007653
Type Construction
Title Construction / Installation of 18" & 12" Pipelines and Remedial Works
Client Snamprogetti / Qatar Petroleum
Date of Completion 03/02/2008
Details The project consists of the removal of defective internally corroded pipelines of 18" connecting KNDS and Jaleha to FNLGCPlant and 12" pipeline connecting Diyab manifold to Jaleha production plant. The works consists of site survey, identification of defective / corroded pipes / bends / spools as per the as-built weld map and PII Integent Pigging Reports, removal and replacement of corroded pipes, valves, etc., internal cleaning, leak testing, functional tests, preservation and re-installation of MOV etc., pre-commissioning and commissioning.
Project No LTC 06/010
Type Construction
Title Replacement of Various Instrument Valves at Fahahil Stripping Plant in the Dukhan Fields
Client Qatar Petroleum
Date of Completion 29/04/2007
Details The project consists of replacement of existing HVCs with bigger capacity valves to increase RAG gas flow, replacement of PCVs with presure control loops on vessels and pressure control to configure in DCS for auto and manual operation.
The work consists of engineering, procurement, construction of civil, structural, mechanical, piping, instrumentation works including cable laying and termination, hydrotesting etc. and pre-commissioning and commissioning.
Project No KT-065
Type Construction
Title Installation of Buried 20" New Fuel Gas Pipeline (Ras Laffan B Combined Cycle Power & Desalination).
Client Siemens / Salam Petroleum / Qatar Petroleum
Date of Completion 10/01/2007
Details The installation works consists of civil, mechanical, scraper traps / pigging, hydrotesting including road crossing (thrustboring/tunneling) and DCVG survey.
Project No GTC /05/162/ED
Type EPIC
Title Engineering, Procurement, Installation and Commissioning of Firewater Tank at Fahahil Stripping Plant and Associated Deluge / Sprinkler System.
Client Qatar Petroleum
Date of Completion 27/11/2006
Details The scope of work consists of EPIC of Tank, Deluge Skids, Valves, Flame Detectors, Flow meters, Control Valves, Cathodic Protection, etc. Also include the works such as Site Survey, Earthworks, Tank Foundations, Excavations of Trenches, Road Crossings, Sleeper Supports, Structural Steel Works, Testing, Calibration, Cable Laying, Lighting System, Calibration of field instruments, F&G systems modification, DCS and other Electrical & Instrumentation works.
Project No GTC/04/194/ED
Type EPIC
Title Engineering, Procurement, Installation and Commissioning of New RAW NGL Injection Facilities at FSP, Dukhan
Client Qatar Petroleum
Date of Completion 15/09/2006
Details This is a multidiscipline project for the installation of new Raw NGL Injection pump & the demolition of existing one with all the related civil and E & I works.
Project No LTC 04/018
Type EPIC
Title Engineering, Procurement, Installation and Commissioning of Upgrade of Instrumentation at PWI 1, 4-9 Stations in the Dukhan Fields (PCR/03/030/D)
Client Qatar Petroleum
Date of Completion 15/08/2006
Details The scope of work consists of Site Survey, Updating of P & ID's, Updating of Specifications, Datas Sheets, etc. Procurement of materials such a transmitters, PCS modifications hardware, bulk instrumentations items, etc. The construction activities consists of installation of new PCS hardware, modification of PCS hardware, installation of new transmitters in the field, calibration of transmitters, installation of new SS process tubing, cabling, etc.
Project No LTC/06/001
Type Construction
Title Maintenance Shutdown Activities at Khuff A & B Station N Plants in Dukhan Fields
Client Qatar Petroleum
Date of Completion 15/06/2006
Details This Shutdown maintenance work of stations and plants consists of process shutdown & isolation, decontamination of vessels, tanks & pigtraps, internal coating of equipments, civil, mechanical, electrical & instrumentation works, rectification and re-installation of valves & motors, nitrogen purging.
Project No GTC/05/155/ED
Type EPIC
Title Engineering, Procurement, Installation and Commissioning of Propane Chillers E1104 A & B At FSP GTC/05/155/ED)
Client Qatar Petroleum
Date of Completion 30/05/2006
Details Project consists of Engineering, Procurement, Installation and Commissioning of New Propane Chiller 2 No. at Fahahil stripping plant and associated Civil and E & I works, each equipment weighing 45 tons of 20 meters long.
Project No 3000005458
Type Construction
Title Construction/Installation of 16" Pipeline from Diyab to Jaleha for Dukhan Field Gas Lifting Project in Qatar
Client Snamprogetti / Qatar Petroleum
Date of Completion 30/09/2005
Details The work consisted of fabrication and laying of 16" pipeline and related works including painting, hydrostatic testing, intelligent pigging and land restoration.
Project No LTC 04/073
Type EPIC
Title Engineering, Procurement, Installation and Commissioning of New Air Compressor at Dukhan Power Station
Client Qatar Petroleum
Date of Completion 10/11/2005
Details The project consists of Design and Detailed Engineering, Procurement, Construction and Installation of Civil / Structural, Mechanical / Piping, Electrical / Instrumentation, Testing / Commissioning and Project Dossiers. The scope include constuction of Building, Compressor Foundation, Fabrication and erection of piping works, installation of compressor, air receiver, dryer, cable laying, field lighting, field instruments electrical panels, control system, etc.
Project No GTC101/ED/04
Type EPIC
Title Engineering, Procurement, Installation and Commissioning of F&G Detection/ Protection & Safety Upgrades in the Dukhan Fields
Client Qatar Petroleum
Date of Completion 11/08/2005
Details Engineering, Procurement, Installation and Commissioning for the F&G detection /protection & safety upgrades in Dukhan fields- The project is a multidiscipline one aimed at enhancing and upgrading the F &G Detection & safety systems in the Dukhan fields, which includes New Fire Water Pumps, Tanks, Deluge Skids, and Associated Instrumentation and Control Systems
Project No GTC/187/ED/03
Type EPIC
Title Engineering, Procurement, Installation and Commissioning of New Instrument Air Compressor Package at PWI Stations- Dukhan
Client Qatar Petroleum
Date of Completion 29/12/2004
Details The scope of work for Air compressor job shall include Design, Detailed engineering, Procurement, Installation, Construction, Pre-commissioning, Commissioning and testing of Instrument Air Compressors at PWI stations PS-1,4,5,6,7,8,9. The air compressors shall be skid mounted, oil injected, rotary screw type units with local compressor control panel, shall be installed at various location in the Dukhan field.
The new units shall be integrated with the existing Instrument air systems, process control and shutdown systems, and are designed to maintain high availability of instrument air.
Project No LTC/142/03
Type EPIC
Title Engineering, Procurement, Installation and Commissioning of Supply & Installation of a New Standby Generator System to Dukhan Jabel Telecoms Room
Client Qatar Petroleum
Date of Completion 08/03/2005
Details Engineering, Procurement, Installation and Commissioning of Supply & Installation of a New Standby Generator to Dukhan Jabel Telecoms Room including Instrumentation and Cabling works..etc
Project No LTC/24/2002
Type EPIC
Title Engineering, Procurement, Installation and Commissioning of Supply, Installation & Commissioning of a Diesel Driven Pump with necessary Modifications at Shahaniya Stations for the Reverse Pumping of Water to Dukhan Through an Existing Pipeline.
Client KAHRAMAA
Date of Completion 25/04/2004
Details To install a Skid mounted Diesel Engine driven Centrifugal Pump with all accessories at Shahaniya Pumping Station to reverse pump approximately One million Imp. Gallons per day (1.0 MIGPD) of potable water from Shahaniya station to QP-Dukhan storage tanks on emergency basis by using the existing 300mm/400 mm/200mm main between Shahaniya and QP-Dukhan Storage tanks with necessary interconnection to the pipe lines with all Electrical and Instrumentation works.
Project No LTC/149/02
Type EPIC
Title Engineering, Procurement, Installation and Commissioning of Replacement of 12" Fuel Gas Line from KMDHS to KMDGS in Dukhan Fields
Client Qatar Petroleum
Date of Completion 15/02/2004
Details Project consists of Complete replacement of existing 12" Gas Pipeline (approx 900 Mtr) including Tie-in and associated Electrical & Instrumentation Works.
Project No LTC/004/02/VO1
Type EPIC
Title Engineering, Procurement, Installation and Commissioning of 4” Khuff Fuel Gas Pipeline to Khatiyah South (Variation No. 1 to LTC/004/02)
Client Qatar Petroleum
Date of Completion 2003
Details Projects consists of Engineering, Procurement, Construction, Installation, Testing & Commissioning of 4" Fuel Gas Pipeline from existing 6" Khuff Gas Line of KSDS. The work consists of Civil, Mechanical, Pipeline, Piping, Instrument & Control, Electrical, Precommissioning and Commissioning.
Project No LTC/004/02
Type EPIC
Title Engineering, Procurement, Installation and Commissioning of 4” and 6” Fuel Gas Pipeline to QNCC and Desalination Plant-Dukhan
Client Qatar Petroleum
Date of Completion 2003
Details Projects consists of Engineering, Procurement, Construction, Installation, Testing & Commissioning of 6" Fuel Gas Pipeline from JDS & QNCC-1 and 4" Pipeline to QNCC Desalination Plant. The works include Civil, Mechanical, Pipeline, Piping, Instrument & Control, Electrical, Precommissioning and Commissioning.
Project No GTC/118/2000
Type EPIC
Title Engineering, Procurement, Installation & Commissioning of Dukhan Flare Upgrade Project
Client Qatar Petroleum
Date of Completion 2002
Details Project consists of Engineering, Procurement, Construction, Installation, Testing and Comissionng of Flare Upgrade Project involving 6 process flare & 4 tank flares, fabrication, K.O. Drum, Pumps, Blowers, ESD Valves, MCC Building Pipeline works of 42", 36", 30" & 24" for 2 km, 3 km, & 4 km, Associated Equipment, Electrical, Instrument and Control System works.
Project No GTC/151/2000
Type EPIC
Title Engineering, Procurement, Installation and Commissioning of 30” Gas Pipeline Replacement from Point W1 to W2 Ras Abu Fontas & Auxiliary Gas Supply to RAF B1
Client Qatar Petroleum
Date of Completion 2002
Details Engineering, Procurement, Construction, Installation, Testing and Commissioning of New Buried 30" Gas Pipeline from Station W1 to Station W2, including all Civil works, Mechanical / Piping and Two Pig Launching / Receiving Station, Fabrication and Erecton Structural steel works and associated Electrical, Instrumentation and F&G works.
Project No GTC/143/EM/02
Type Construction
Title NFGP/AGRU/SRU Modification Works to Meet NGL-4 Project Feed Gas Requirements
Client PETROFAC
Date of Completion 2002
Details AGRU/SRU Sea Water Upgrade Project in NGL was a Fast Track Project which include Enginering, Procurement, Construction and Comissioning. The project was to Upgrade Sea Water Headers from Cement Lined to GRE Piping , Installation of new equipment such as Sea Water Fillters, Dry Gas Coolers and Instrumentation. The scope includes Carbon Steel Heavy Wall Piping, GRE Pipeline & Piping, Cement Lined Piping Modification, Tie-ins and related Civil, Strucutural, Trecnhing and works inside Live Plants of NGL Mesaieed. The works include Electrical, Instrumentation and Control Systems. Total of 220,000 Manhours spended in 2.5 Months.
Project No GTC/197/ED/01
Type EPIC
Title Engineering, Procurement and Construction of 12” Pipeline for Arab-D Condensate
Client Qatar Petroleum
Date of Completion 2002
Details Engineering, Procurement, Installation and Commissioning of approximately 3 km 12" pipeline including All Fabrication works related to the construction of 12" Pipeline, Structural Steel works etc. It was a Fast Track Project
Project No GTC/124/01
Type Construction
Title Rehabilitation of Crude Oil Tanks QJA-1 and QJA-24 in the Dukhan Field Area
Client Qatar Petroleum
Date of Completion 2001
Details Work Consiste of fabrication, installation and testing of replacement parts of the Tank including structural members , Tank Calibration, Testing and Commissioning of the existing crude oil storage Tank
Project No LTC/013/00
Type Construction
Title Construction of Diyab Enhanced Oil Recovery (EOR) Pilot Test Arab "D" Dukhan
Client Qatar Petroleum
Date of Completion 2001
Details All work\s Related to Fabrication, laying, Welding, NDT, Hydrotestng, etc. including all associated structural steel supports and platforms of Pipng Structural Steel works
Project No LTC/028/00
Type Construction
Title Construction of 6" Khuff Gas Feed Buried Pipeine to Dukhan Power Stations in the Dukhan Fields Area
Client Qatar Petroleum
Date of Completion 2001
Details Fabrication, laying, welding , NDT, Hydrotesing of pipeline , including all required support sleepers, Pig launching,receiving station etc.
Project No LTC/016/00
Type Construction
Title Plant Shutdown works at Various Degassing Stations in the Dukhan Fields Area
Client Qatar Petroleum
Date of Completion 2000
Details Maintiance and repair works of various Sections of the Plant, cleaning, re-assembly of vessel & Replacement of parts etc. during shutdown. Including related Electrical & Instrumentation maintenance works.
Project No GTC 110/97
Type Construction
Title Construction, Installation and Hook-up of PWI Spurlines and Oil Flowlines in Dukhan Fields (1997-1999 Programme)
Client Qatar Petroleum
Date of Completion 2000
Details Fabrication, laying, welding , NDT, Hydrotesing of pipeline (12", 10" & 6") , including all required support sleepers, Pig launching,receiving station etc. Including related Instrumentation and Control Systems for approx. 100 km.
Project No LTC/086/98
Type EPIC
Title Engineering, Procurement, Installation and Commissioning of Point “W” 2 Station Low Flow Pressure Letdown Facility , at Ras Abu Fontas
Client Qatar Petroleum
Date of Completion 1999
Details Engineering, Procurement, Installation and Commissioning of 30" Gas Pipeline approx. 5 km including Fabrication works of Plant Piping, related Structural Steel works, Electrical and instrumentation works, etc.
Project No LTC/278/97
Type Construction
Title Isolation MOV’S for Crude Oil Incoming Line to Terminal and Provision of Actuator for Existing Manual Valves, Mesaieed
Client Qatar Petroleum
Date of Completion 1999
Details Automation of existing manual valves including procurement and supply, fabricaton of necessary parts and installation of nescsary control system in the crude oil loading terminal at Mesaieed.
Project No LTC/182/98
Type EPIC
Title Procurement and Installation of Knockout Pot for Fuel Gas Treatment in the Dukhan Power Station
Client Qatar Petroleum
Date of Completion 1999
Details Procurement, supply, Installation, testing and commissioning of Knock out pot and fabrication and erecton of associated piping/structural work for fuel gas treatment in dukhan power station
Project No LTC/258/98
Type Construction
Title Plant Shutdown works at Khuff ‘B’ ‘C’ & ‘D’ Plant in the Dukhan Fields Area
Client Qatar Petroleum
Date of Completion 1999
Details Overhauling, servicing, testing, commissioning and strat-up of plants during shutdown and Manpower Support service
Project No LTC/173/98
Type Construction
Title Replacement of 30” Khuff Gas Pipeline from Point “N” to “B” in the Dukhan Fields Area
Client Qatar Petroleum
Date of Completion 1999
Details Inspection, replacement of corroded section of existing pipelines, NDT, Hydrotesing and commissioning, of existing 30" Khuff Gas Pipeline with related instrumentation works.
Project No GTC/198
Type Construction
Title Replacement of 30" Khuff Gas Pipeline Point K-1-N
Client ZAKHEM International
Date of Completion 1999
Details Replacement of 30" Khuff Gas Pipeline Point K1-N.
Project No ARAB - D
Type Construction
Title Dukhan Arab “D” Gas Recycling Project Maintenance Works-Dukhan
Client BROWN & ROOT
Date of Completion 1999
Details Modification works to Piping, Structural Steel, E & I and Control Systems Works during Maintenace Period of the Arab-D Plant At Dukhan
Project No GTC/107/96
Type Construction
Title Dukhan Arab “D” Gas Recycling ProjectPart:Headers/flowlines/ Wellhead/ Waterlines / Civil Works
Client HDEC / B&R / QGPC
Date of Completion 1998
Details Fabrication, Laying, welding, NDT various spurlines, including Hydrotesing & commissioning for Arab-D Plant Construction including 24", 8" & 2" pipeline for 45 km, 25 km & 60 km.
Project No GTC/113/97
Type Construction
Title Rehabilitation of Crude Oil Storage Tanks QJA-22/23 at Khatiyah and QJA 25/26 at JDS-Dukhan
Client Qatar Petroleum
Date of Completion 1998
Details Work Consists of fabrication, installation and testing of replacement parts of the Tank including structural steel , Tank Calibration, Testing and Commissioning of the existing crude oil storage Tank
Project No LTC/155/97
Type Construction
Title Potable Water Supply to Bir Zekrit Village and Army Post-Dukhan
Client Qatar Petroleum
Date of Completion 1998
Details Project consists of Enginering, Material Procurement, Fabrication, laying, Welding, NDT, Installation and testing of Potable water pipeline, hydrotesting, pigging , structural steel supports, precasting concrete sleepers.
Project No LTC/065/98
Type Construction
Title Plant Shutdown works at Khatiyah and Fahahil Stations in the Dukhan Field DUKHAN AND DOHA OFFICE
Client Qatar Petroleum
Date of Completion 1998
Details Work Consiste of fabrication, installation and testing of replacement parts of the Tank including structural steel , Tank Calibration, Testing and Commissioning of the existing crude oil storage Tank with related electrical / instrumentation maintenance works.
Project No LTC001/98
Type Construction
Title Plant Shutdown works at Khuff ‘E’ and ‘G’ in the Dukhan Fields Area DUKHAN AND DOHA OFFICE
Client Qatar Petroleum
Date of Completion 1998
Details Work Consiste of fabrication, installation and testing of replacement parts of the Tank including structural steel , Tank Calibration, Testing and Commissioning of the existing crude oil storage Tank
Project No GTC/102/96
Type EPIC
Title Engineering, Procurement and Construction of Oil Flowlines and Wellhead –Dukhan
Client Qatar Petroleum
Date of Completion 1997
Details Fabrication, laying, welding , NDT, Hydrotesing of pipeline , including all required support sleepers, Pig launching,receiving station with related electrical & instrumentation works.
Project No GTC/160/95
Type EPIC
Title Engineering, Procurement, Installation and Commissioning of Cathodic Protection System upgrade (Pipelines) Dukhan
Client Qatar Petroleum
Date of Completion 1997
Details This project which was executed on turnkey EPIC basis, comprised of Detailed Engineering, Procurement, Installation and Commissioning of Impressed Current Cathodic Protection System for 301 KM of underground Oil & Gas Pipeline - network, scattered from Doha to Dukhan, Dukhan to Umm Bab and Umm Bab to Point B near Mile 42. This included 30” gas lines (64 KM), 24” gas line (38 KM), 20” gasline (41 KM), 18” gasline (32 KM), 16” gas line (18KM), 12” condensate line (42 KM) and 10” oil line (66KM), with associated Electrical, Instrumentation and Control Systems.
Project No GTC/145/95
Type EPIC
Title Engineering, Construction of Oil flowlines and Wellheads Piping Upgrade – Dukhan fields, 1995 Programme-Dukhan
Client Qatar Petroleum
Date of Completion 1996
Details Fabrication, laying, welding , NDT, Hydrotesing of pipeline , including all required support sleepers, Pig launching,receiving station etc. with related E & I works.
Project No GTC/152/95
Type Construction
Title Rehabilitation of Crude Oil Storage Tanks QJA-3,4,22 & 23 at Fahahil and Khatiyah main Stations-Dukhan.
Client Qatar Petroleum
Date of Completion 1996
Details Work Consists of fabrication, installation and testing of replacement parts of the Tank including structural steel , Tank Calibration, Testing and Commissioning of the existing crude oil storage Tank
Project No CC/181/95
Type EPIC
Title EPIC works related to Improving Water disposal Facilities at Khatiyah main & Fahahil main Degassing Stations and Routing of Produced Water to Disposal Well at the Khatiyah North Degassing Station
Client Qatar Petroleum
Date of Completion 1996
Details EPIC works related to Improving Water disposal Facilities at Khatiyah main & Fahahil main Degassing Stations and Routing of Produced Water to Disposal Well at the Khatiyah North Degassing Station including related electrical / instrumentation and control systems works.
Project No CC/186/95
Type Construction
Title Replacement of Suction Strainers and Recirculation Lines at PWI Pump Stations At Dukhan
Client Qatar Petroleum
Date of Completion 1996
Details Fabrication, laying, welding , NDT, Hydrotesing of pipeline , including all required support sleepers, Pig launching,receiving station etc.
Project No GTC112/95
Type Construction
Title Installation of Powered Water Injection (PWI) Spurlines Dukhan – 1995 Programme Dukhan
Client Qatar Petroleum
Date of Completion 1996
Details Fabrication, laying, welding , NDT, Hydrotesing of pipeline , including all required support sleepers, Pig launching,receiving station etc. with related electrical and instrumentation works.
Project No LTC/067/96
Type Construction
Title Emergency Remedial works 30” Khuff gas Line at Point ‘N” in the Dukhan Fields Area
Client Qatar Petroleum
Date of Completion 1996
Details Fabrication, laying, welding , NDT, Hydrotesing of pipeline , including all required support sleepers
Project No CC/180/95
Type Construction
Title Vessel Inspection and Mechanical Related works at Khuff Plants ‘H’ and ‘L’ in the Dukhan Field Area
Client Qatar Petroleum
Date of Completion 1996
Details Overhauling, servicing, testing, commissioning and strat-up of plants during shutdown and Manpower Support service
Project No CC/194/95
Type Construction
Title Vessle Inspection and Mech. Related works at the Jleha Dehydration Mol-Sieve & Umm Bab Booster Stations in the Dukhan Fields Area
Client Qatar Petroleum
Date of Completion 1995
Details Overhauling, servicing, testing, commissioning and strat-up of plants during shutdown and Manpower Support service
Project No CC/171/95
Type Construction
Title Engineering Procurement and Constr. Of 4" Potable Water Line Replacement, Sinnah- Dukhan
Client Qatar Petroleum
Date of Completion 1995
Details Project consists of Enginering, Material Procurement, Fabrication, laying, Welding, NDT, Installation and testing of Potable water pipeline, hydrotesting, pigging , structural steel supports, precasting concrete sleepers and related E & I works.
Project No CC/010/95
Type Construction
Title Construction & Hook-up of Oil Flowlines Dukhan Fields 1995 Programme Phase I
Client Qatar Petroleum
Date of Completion 1995
Details Fabrication, laying, welding , NDT, Hydrotesing of pipeline , including all required support sleepers, Pig launching,receiving station etc.
Project No CC/049/95
Type Construction
Title Upgrade Wellhead Facility at Dukhan field Safety Survey
Client Qatar Petroleum
Date of Completion 1995
Details Survey of Dukan Wellhead Facility